Operations Authorization (Onshore)
Purpose of the Operations Authorization
The purpose of the Operations Authorization (OA) is to ensure that the Proponent has the necessary plans and competencies in place to carry out the work or activity that has been proposed. The OA is intended to promote the safety of workers and the public, the protection of the natural environment, and the conservation of oil and gas resources.
Overview of the Operations Authorization
The authority to issue an OA is provided by section 6 of the (NWT) Oil and Gas Drilling and Production Regulations (OGDPR). OAs are issued for exploratory, drilling and production activities; however, the authorization is more detailed for production activities.
Process Milestones
The Operations Authorization process consists of three milestones. A “milestone” is a major step in a process that involves a key action taken or decision made. Each milestone, in practice, consists of one or more “steps” which describe the mechanics of how the authorization is processed. For more information on the process steps and activities that are conducted within each step, contact us.
Milestone 1 - Application submitted
Milestone 1
- Step 1 – Application for Operations Authorization is submitted by Proponent to the Office of the Regulator of Oil and Gas Operations (OROGO)
Milestone 2 - Autorization determination
Milestone 2
- Step 2 – OROGO considers the application and conducts a technical review
- Step 3 – The Proponent responds to information requests (if necessary)
Milestone 3 - Authorization issued
Milestone 3
- Step 4 – OROGO determines whether application is approved; NWT-PRR approves OA under OGOA
- Step 5 – (if OA is not approved) Proponent may revise and resubmit application
- Step 6 – (if OA is approved) Letter of Authorization (with terms and conditions) is issued by OROGO
In addition, this milestone is influenced by one external activity (which occur immediately prior to Step 4):
- If the Operations Authorization is for exploration activities, confirmation that a Benefits Plan has been approved, or the requirement waived, is required.